1、3.5 Construction Statements for the Steel Liners Erection3.5.1 Preparation at the construction site: The embedded items will be installed along with the rising construction platform, complying severely with the requirements of the drawing (see the drawing).3.5.1.1 After the steel formworks have been
2、 promoted, the platform will be applied to carry on the installation of elevator bearers and wires, hanging the steel wires for elevating circular platform, conducting the reinforcement of pulleys through the application of the elevator in the center, and installing of limit device and suspension lo
3、ops and so forth.3.5.1.2 In prior to the removal of promote platform, the 193m platform will be installed through the application of the jumpform of construction platform. After that, a 2t winch will be lifted to the platform in a appropriate distance of 3-4m to the elevator as the fixing position.
4、The 193m platform will also be utilized to install the 180m platform. And similarly it comes to the 140m one.3.5.1.3 After the promote platform removed, the distribution of cables will be conducted by the utilization of human-and-cargo elevator and cage, as well as installing, fixing and debugging f
5、or the winch. Meanwhile carry on the installation and welding of suspension points, and steel wire hanging at the 140m platform.3.5.1.4 Before the steel liners have been hoisted, a railway rolling chute will be laid in the midst of the preformed hole at the bottom of chimney stack, on which a manpow
6、ered vechicle was installed to take the steel liners in place and carry out the upset transportation from the storage yard to the erection position.3.5.1.5 The winch on the promote platform will be employed to fix the welder, winch, and the side basket as the vertical tranporting tools for platform
7、and hydraulic lifting equipments. And in ahead of lowing-down, the installation and welding of lateral bearer, bearers of suspension points and elevator, and guide pulleys on the top must be completed and in preparation.3.5.1.6 The leveling, setting out and embedded items of the pedestal of steel li
8、ner should be examined and kept with records to prepare for the febrication and installation.3.5.1.7 Preparation for hydraulic lifting equipment: it must be tested and in preparation. There will be one 5t two-tube winch, one 5t winch, one 2t winch, two 3t winches installed and in preparation. The hu
9、man-and-cargo elevator can be available after it has been debugged and tested with its net load. 3.5.2 Operational ProcedureThe six layers of platforms, straightened ladders, winding stairs, components and embedded items will be manufactured in advance as well as the steel flues will also be febrica
10、ted at site. The fabrication process is: raw material accessing to the yardverifying the specification and certification of materialcarrying out the stretching , bending, percussion and welding testtemplate-makingfabrication & preparation on the materialalignment of componentsbeing compressed into f
11、ormationcombination and jointinginspection on the processweldingexamination and alignment for deformational partsmaking holesself-inspection and specilized examinationcleaning up the footing coarse of metaldust removel, oil-painting and corrosion protectionpiling-up and numbering of semi-manufacture
12、d products.With the template-making, the sample plates and items must be made, complying with the right shape and dimension and a proportion of 1:1 indicated on the work drawing, and being coodinated with relevant clamping fixture. Only after the sample plate has been to transmit to the technical st
13、aff and inspector and given by permittion, it can be carried out with its febrication, of which the drawing number, names of components, certification and specification of material must be signed. And preserve enough amount according to different processing measures. For the large sheet material, it
14、s geometry dimension, side length and diagonal lines must be controlled and verified, as well as accumulated error considered for the item consists of multiple components. Both corrosion protection of final product members and footing course treatment need be in accordance with design and specificat
15、ions, and make sure the adhensive strength between the membrane and primer. And the painting thickness and layers must be controlled stricktly as well as the material diluted comply with the mixing proportion. The storage yard for steel members must be flat and with no contamination and accumulated
16、water, and the workpieces must be supported firmly with no displacement or sedimentation permitted. Numbering must be conducted, and give clear indication of the setting-out line and center line at the same time. For those special ones , their schematic points , names and elevation should be symblol
17、ized to facilitate for the verification and transportation. 3.5.2.1 Manufacture of steel platform, windingstairs, restraining points and streightened ladders:3.5.2.2 According to the work drawing , the appearance, arc of processing, dimension, and sign number of members accessing to the site must be
18、 dealed with examination and acceptance, for which the unqualified ones cannot be put into operation. As a result of special condition, the 193m, 180m, 140m platforms will be elevated and installed in prior to the other three platforms.3.5.2.3 In the reason that all the platforms, steel stairs, fenc
19、es are final products, there wouldnt be instructions on the manufacturing procedure in these statements.3.5.2.4 Each member of the platforms, steel stairs and fences must be marked with the platform and supporting number, and meanwhile the manufacturer should also provide numbered drawings in detail
20、, which was kept to prevent an unnecessary waste of human resources. For instance, the 180m platform should be marked with 180-1, 180-2180-8.3.5.2.5 The hole-making between installation position on the beam and relevant connectors must be conducted by one time. Standard joints should be adopted for
21、all the circular and main beams, which cannot be distributed on the center of arc or node. And the structural corrosion protection must be practiced segmentally. For the hiden area, it must be carried out firstly, and the supplemental action must be implemented after welding. Welding material and el
22、etrodes must be in accordance with given conditions on quality. For example, E43 series of eletrodes were adopted for A3 steel.3.5.2.6 The fabrication of restraining circular plate should be done comply with the external radius of different tubes.3.5.2.7 For the configuration of pedestal plate, it w
23、ill be cut on average in accordance with different material. The weld bonds will be staggered as well as foundation bolts compressed. Three pieces will be assembled, for which a few weld bonds are preserved to be on the pedestal. The setting-out of holes must be configured strictly with the bolts. T
24、he weld bonds of pedestal are single groove, others are double groove, which makes double formation. And before the steel flue was erected, the pedestal must be in position and compressed, numbered with stiffners at support.3.5.2.8 Breeching opening and box structure fabrication and assembling: Seti
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- X330 火力 发电站 烟囱 钢内筒 施工 方案 英文

链接地址:https://www.desk33.com/p-1268040.html