1、GLOBAL PURCHASINGSupplier Technical AssistanceEdition 1, October 2002Phased PPAP Phased Production Part Approval ProcessPhased PPAP Ford Motor CompanySupplier Technical AssistanceOctober, 2002Table of ContentsAcknowledgements Foreword CONTENTSPhased PPAP Introduction3PPAP Milestones4Phased PPAP Over
2、view5Phased PPAP Process Flow6Run-at-Rate7Phase 1 PPAP Quality Verification8Phase 2 PPAP Production Verification9Phase 3 PPAP Capacity Verification10Customer Disposition of the PSW13Expectations14Appendix A15Appendix B21Appendix C22Appendix D24AcknowledgementsThe development of Phased PPAP and the s
3、upporting systems has represented a substantial undertaking. We would like to thank the members of the Ford development team as well as acknowledge key suppliers for their time and effort in this project, including: Dana Lear Magna Meridian Automotive SY Systems Technologies TRW VisteonForeword Phas
4、ed PPAPVision Partner with suppliers to drive flawless execution in vehicle launch and deliver products that surpass customer expectations.TeamworkFord Motor Company and its suppliers must work together to deliver a quality part, produced on-time, that meets all Ford engineering requirements. To acc
5、omplish this goal, Ford and its suppliers must place trust, integrity and accuracy above all else in the Production Part Approval Process.Supplier Responsibility in Flawless LaunchSupplier delivers a successful launch with no quality or capacity issues that affect the Ford production process. What P
6、hased PPAP Means to Ford Motor CompanyPhased Production Part Approval Process (PPAP) is the process in which the supplier demonstrates they can produce quality parts and provide these parts to Ford at the required volume. Successful completion of Phased PPAP demonstrates supplier readiness using the
7、 production machinery, tooling, and facilities with the intended personnel at the intended production rate that is capable of meeting the Ford required volumes (as specified on the Request for Quotation).Phased PPAP IntroductionAs a result of reviewing industry best practices, Ford has modified PPAP
8、 into a three phased approach that will independently verify product quality, production readiness and capacity prior to Job #1. Phased PPAP will provide the launch team with an improved method of risk management and provide a consistent method for a supplier to determine if they meet Ford projected
9、 program volumes (See Appendix A). Phased PPAP ensures that the supplier process has the potential to produce a quality product that consistently meets Ford requirements during an actual production run at the quoted production rate.Phased PPAP separates the PPAP process into three phases: q Phase 1
10、is called Quality Verificationq Phase 2 is called Production Verificationq Phase 3 is called Capacity Verification.This Phased approach requires the supplier to provide promise dates to Ford for each of the three events, and additionally includes the requirement for the supplier to indicate that Run
11、 at Rate has been successfully completed. (Appendix B, Table 1 summarizes these requirements)Note: For less complex components/commodities/production streams, it is possible to complete multiple phases as a single event.Phased PPAP OverviewScopePhased PPAP redefines both the interpretation and execu
12、tion of the Production Part Approval Process (PPAP) (including the Part Submission Warrant (PSW) and is required for the following:1. A new part or product (i.e., a specific part, material or color not previously supplied to the specific customer).2. Correction of a discrepancy on a previously submi
13、tted part.3. Product modified by an engineering change to design records, specifications, or materials.4. Any situations required by Section I.3.1 from the AIAG PPAP Manual, 3rd Ed. (See Appendix C).These requirements are a minimum; local operations may require additional approvals.Phased PPAP will
14、eventually be applied globally in the Production Part Approval Process. Suppliers are required to apply the Phased PPAP process, including promise dates, confirmation and event completion for all new tooled parts.Phased PPAP applies to both new vehicle programs and for vehicles currently in producti
15、on, i.e. running changes. Benefits of Phased PPAPSuppliers and Ford will benefit from the use of Phased PPAP. Phased PPAP: Requires planning for launch Divides PPAP activities into more manageable segments Ensures assessment of supplier ability to handle production volume Provides a consistent mecha
16、nism to determine capacity verification Provides the program team with additional measures to forecast program readiness Provides clarity to the existing PPAP process Phased PPAP MilestonesPhase 2Phase 3Phase 1Quality VerificationCapacity VerificationProduction VerificationThe complete actual produc
17、tion stream (tool, line, facilities, personnel, etc.) intended for this specific program / launch is in place and operationalDimensional, Lab and ES testing complete from all tools, cavities, molds, production streams (including all appearance approvals)Supplier submits Part Submission Warrant (PSW)
18、.Parts are produced from the complete actual production stream (tooling, equipment, facilities, personnel)Capacity Verification is demonstrated by yielding quality parts to meet a minimum of one day of Ford production ( Daily Planning Volume DPV)Parts are produced from a minimum of one production st
19、ream (tool, line, facilities, etc.)Dimensional, Lab and Engineering Specification (ES) testing complete for this production stream (less appearance approvals)Initial Run at RateParts produced from a production stream (from a minimum of one production tool / line / process stream) at production feeds
20、 and speeds.Provides an early indicator if supplier can make future timingParts from the initial Run at Rate may be used for Phase 1 and Phase 2.Reference: Ford Product Development System (FPDS)J1LR*CCCPPAPHSCSI1/2PS KO*Note: 1PP Build occurs during Launch Readiness phase of FPDS, which is 4.5 month
21、s prior to J1 for an S3 and above program. Supplier completes Capacity Verification (Phase 3 PPAP) target completion is 4 weeks prior to Job 1 - demonstrating ability to meet Ford required volumes under intended operating pattern supplier dispositions completion and provides Demonstrated Weekly Capa
22、city numbers in systemSupplier completes Production Verification (Phase 2 PPAP) for specific program / plant by In Plant Date for 1PP build phase (all 19 elements of PPAP on parts from actual production streams (tools/cavities/molds/lines/etc.) supplier dispositions in system and forwards PSW docume
23、ntation.Supplier completes Quality Verification (Phase 1 PPAP) (16 of 19 elements of PPAP - excludes PSW, Appearance Approval and Master Sample) supplier dispositions in systemSupplier completes a minimum of one production stream and performs initial Run-at-Rate supplier indicates successful Run-at-
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 汽车 阶段性 PPAP 英文
链接地址:https://www.desk33.com/p-15190.html