F2-F3SurveyingMethodology公路项目测量方案中英文.doc
《F2-F3SurveyingMethodology公路项目测量方案中英文.doc》由会员分享,可在线阅读,更多相关《F2-F3SurveyingMethodology公路项目测量方案中英文.doc(14页珍藏版)》请在课桌文档上搜索。
1、-Content1Introduction介绍22 Horizontal Control Point Establishment (HCPs)2建立水平控制网2.1 GPS Survey (GPS Observation)2GPS观测,GPS测量2.1.1 Establishment of primary control point2建立首级控制点/网2.1.2 GPS Technique2GPS技术2.1.3 Referenceand Datum2参考和技术参数2.2 Traverse Survey2导线测量2.2.1 Establishment of secondary control p
2、oint2建立加密(次级)控制点/网2.2.2 Traverse adjustment2平差(加密控制网平差)2.2.3 Accuracy required and achieved2所需的精度和所到达的精度(是否符合要求)3 Vertical Control Point Establishment (VCPs)2建立垂直控制网3.1 Differential leveling2精细水准测量3.2Permissible error formula2允误差的公式4 Detail Surveying2测量详述4.1Route Location2中桩确实定(定线)4.2 Cross Sections
3、2横断面测量4.3 Longitudinal Section2纵断面测量5 Resources Allocation Plan2人员与设备配置方案5.1 Personnel Deployed2测量人员的配置5.2 Instrument and software2设备配置和(数据处理)软件1 Introduction引言Topographic survey is one of the most important and crucial form the base data for the project construction. The topographic survey is basic
4、 pre-requisite to capture all the physical feature along the project corridor to enable the selection of feasible and most useful alignment and later to design and to facilitate the establishment of final centerline of the road project and land acquisition requirements. The topographic survey work m
5、ethodology consists of following main tasks. 地形测量是施工工程的根底数据最重要也是最关键式之一。测量是获取所有工程沿线的物理特征的首要任务,使得可行路线的选择得以施行,此后使得设计和最终中心线的埋点布设以及土地征用的工作得以顺利开展,测量案包括以下主要任务: Route location.路中心线的初测(定线) Setting up of permanent beacons to serve as a reference system during construction of road project.建立永久控制点标志在作为道路施工过程中的参
6、照系统 Development of control traverse-line and geometric level-line.建立导线(平面控制)和水准线(水准路线) Detailed field survey using Total Stations and Automatic Levels, which will have a different precision according to the topographic operations.现场测量要使用全站仪和自动安平水准仪,根据测量操作,两者有不同的精度 Data Processing and CAD. CAD和数据处理 D
7、elivery of survey report including Diagrams and Monographs.提交包括图表和文字性的阐述的测量报告 Ground surface andstructural location survey.地形测量和构造性的地物测量For carrying the survey work the contractor received two initial control points from Enyi Consultant and collected detail data related to national Bench Mark in the
8、 project corridor and deployed high precision instruments like GPS, Total station, and Auto Level in pliance with the TOR. The contractor will verify the reliability of the EMA control point and known GPS points(GPS 11 & GPS 11A) in the field before they are used.为能使测量工作得以实施,施工从Enyi公司处得到引向工程路线的两个初始控
9、制点,并收集到与控制网严密关联的基准点详细数据。此次测量配置了高精度仪器比方符合TOR规标准的GPS,全站仪和自动水准仪。在引点使用前,承包会校验所得到的EMA控制点和现场GPS11和11A的可靠性。. z.-2 Horizontal Control Point Establishment (HCPs)建立水平控制网2.1 GPS Survey (GPS Observation)GPS测量(观测)2.1.1 Establishment of primary control point建立首级控制点/网Global Positioning System (GPS) observations wi
10、ll be fi*ed at 3 km intervals along the center line. The geodetic GPS Points will be placed in highly accessible sites with appropriate standard concrete benchmarks and bed rocks which are painted yellow, protected against impact to guaranty their stability and integrity.在沿中心线每隔3公里处进展GPS观测。GPS控制点使用标
11、准混泥土或在岩上喷上黄漆作为基准点,并设在容易接近的场地,而且加以保护防止撞击确保控制点的稳定性和完整性。2.1.2 GPS Technique GPS技术要求The observations will be carried out with 3 units of Leica GPS-System Dual-frequency receivers using Static Mode by tracking minimum 8 satellites per site in order to determine 3-D WGS84 co-ordinates. 测量工作使用3组莱卡的GPS系统双频接
12、收器,并使用静态模式,每个位置跟踪至少8个卫星,以便定位3-D WG84坐标。The contractor will transferEnyis control point (GPS 11 & GPS 11A) to TP 1 which is around 3km from the GPS 11 and found in the nearby mountain. Then the GPS observation from TP1 to F2-F3 starting point (GPS 1) will proceed. The baseline measurement will mainta
13、in an accuracy level of10 mm+5ppmwith at least45 minutes of observation.承包会从Enyi控制点GPS 11和GPS 11A导到TP1, TP1位于附近的山上距离GPS11大概有3公里,接着将从TP1到F2-F3的起始点(GPS1)开场GPS观测。这个基线测量至少观测45分钟并保持在精度10 mm+5ppm围。Using highly post-processing GNSS Solutions software, the WGS84 co-ordinates transformed into the National Gr
14、id, U.T.M. co-ordinates based on Calarc 1880 (Modified) Spheroid - Datum: Adindan (30th Arc).使用高精度GNSS后处理软件,基于Calarc 1880(修正后) 椭球体坐标-参数:Adindan (30th )弧度,将WGS84坐标转化成网坐标。A clear and intelligible monograph of the verte*es with a brief description of the location, photograph and diagram for each of thi
15、s will be prepared and attached.此后,我会为每个测量点准备一份清楚明了的并附有简单位置描述以及图表照片的测量报告。2.1.3 Reference and Datum参照和数据参数To secure and validate reasonable initial point, the remaining new primary control points will be automatically tied to the national grid system.为确保和证实初始点的合理性,之后建立的首级控制点会自动关联网系统。The transformatio
16、n requirements used to correlate the surveying work with national grid system of Ethiopia using GNSS software is as follows: 转点要求测量工作要与埃塞的网系统严密关联,要使用如下GNSS软件:- Coordinate system坐标系统Name-WGS 84 UTM zone 36N名字-WG84UTM 36区北Type Projected类型-投影Unit Meters单位-米Vertical datum- OGSM02垂直数据-OGSM02-Datum数据Ellip
17、soid name-CALARC 1888椭球面命名-CALARC 1888Semi-major A*is-6378249.145半球-主轴心-6378249.145Inverse Flattening-293.466076740反转展平-293.466076740D* to WGS84-165.000mDY to WGS84-11.000mDY to WGS84- 206.000mR* to WGS84- 0.000000mRY to WGS84- 0.000000mRZ to WGS84- 0.000000mPpm to WGS84- 0.0-Projection投影Projection
18、class- Transverse_ Mercator投影级别- Transverse_ MercatorLatitude of origin- 0000 00.00000N原点维度- 00 00 00.00000北Central meridian - 330 00 00.00000E中央子午线- 330 00 00.00000东Scale factor -0.0比例系数-0.0False easting- 500000.000m伪东向分量- 500000.000米False northing- 0.000m伪北向分量-0.000米-Units单位:Angular measurements a
19、re taken by degree and linear measurements are done and e*pressed by meters.角测量用度表示, 线性测量用米表示。2.2 Traverse Survey导线测量2.2.1 Establishment of Secondary Control Point建立加密(次级)控制点/网Benchmark (secondary control points) referenced in the field on reliable points on appropriate beacons protected against imp
20、act to guaranty their stability and integrity. These benchmarks will be established at 100-500m intervals prior to initiation of the survey work as stipulated in the TOR or as deemed necessary to suit with the site conditions. Care will be taken while establishing these points to locate them at safe
21、 places within the Right of Way (ROW) and away from main construction area to ensure no disturbance to the permanent benchmarks during construction period. These points will be established by the available materials on the site such as bed rocks and fi*ed bolder stones painted white and crossed by c
22、hisel on the top.恰当标志杆标识出的现场可靠加密控制点作为参照引用并加以保护确保它们的稳定性和完整性。按照TOR规定或根据现场实际情况,这些基准点布控要先于测量工作前开场,其间距在100到500米之间。布设这些控制点时要小心慎重,放在道路用地的平安位置并要远离主要施工区域以确保施工期间不干扰这些永久性基准点。这些控制点的布设使用现场可用的物料,比方喷上白漆的岩床和固定巨,用顶部穿插开凿。Lists of all benchmarks will be tabulated with the following details and attached in Anne*es.所有基准
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- F2 F3SurveyingMethodology 公路 项目 测量 方案 中英文
链接地址:https://www.desk33.com/p-21230.html